LAHQRE (PR) - Nespak is reviewing the detailed design and supervising the construction of 425MW Combined Cycle Power Plant at Nandipur which is being constructed by M/s Dongfang Electric Corporation Limited (DECL) of China at a cost of $329 million. A joint meeting was held among Pepco, Nespak and DECL in March 2010 to discuss outstanding technical issues, review of the progress of design, manufacturing / supply of equipment and construction activities of the Project. Meanwhile, under Nespak supervision, all piling works and foundations of gas turbine generators, heat recovery steam generators and ring foundations for ten fuel oil tanks have been completed while foundations for various equipment are in progress. Fabrication of fuel oil tanks and 2.4 meter dia cooling water pipeline is also in progress at the project site.