Islamabad - Construction work on 25.6-kilometre Peshawar More to New Islamabad Airport Metro Bus Service is likely to be completed by end of April.

National Highway Authority (NHA) spokesman Kashif Zaman said that all bridges of Package-I and IV had been completed while over 80 per cent of the bridges of Package-II and III had also been completed. He said that all underpasses of the project had been completed except those in the Package-III while overall, he said, 92 per cent of the underpasses had been completed. He said that all the culverts of the projects had been completed. He said that over 80 per cent progress had been achieved on civil works of the first three packages while 94 per cent progress has been achieved on the last package.

The project has been divided into fo4ur packages including Package-I from Peshawar More to NUST, Package-II from NUST to GT Road, Package-III from G T Road to Motorway Interchange and Package-IV from Motorway Interchange to the New Islamabad Airport.