Islamabad - The Capital Development Authority (CDA) would start giving possession of plots to the allottees of Park Enclave housing project from December 28, 2015, CDA officials said yesterday.
Initially, possession in the areas where 100 percent development work has been completed will be given while possession in the areas where final touches are being given will be handed over by February 2016, they said. Chairman CDA Maroof Afzal visited the site of Park Enclave and reviewed the progress of ongoing development work.
The project director of Park Enclave Housing Project briefed the chairman about the progress of development activities. He apprised that development work on this project remained stalled for years, however, sitting CDA management not only prioritised the project but also devised an effective plan and started development work in August last year.
Maroof Afzal directed the project director to ensure completion of work in the next few days so that possession could be handed over by December 28, 2015.