LAHORE-Gulpur Hydropower Project has achieved certified commercial operation and has been producing cheap electrity for the national grid, said Dr Tahir Masood, Managing Director NESPAK in a statement on Wednesday.
NESPAK in a joint venture with M/S MWH Inc. USA has provided consultancy services as Owner’s Engineer to M/s Mira Power Limited, a subsidiary of KOSEP, South Korea, for the 102 MW Gulpur Hydropower Project.
NESPAK provided technical support to Mira Power Limited in getting approvals from different government agencies as well as supporting the EPC Contractor in resolving complex issues arised during construction. NESPAK was also involved as Owner’s Engineer in development and completion of 84MW New Bong Escape Hydropower Project, which is the first hydro IPP of Pakistan, thus becoming a leading consultancy firm in development of private hydropower project in Pakistan.
Gulpur Hydropower Plant is a run-of-the-river hydroelectric generation project located on Poonch River, a major tributary of Jhelum River near Gulpur in Kotli District of Azad Kashmir. The project financing has been provided by Korea Exim Bank, Asian Development Bank (ADB), International Finance Corporation (IFC), The Islamic Development Bank and ECO Bank. The project is developed under Government of Pakistan’s Policy for Power Generation Projects 2002 as adopted in Azad Jammu & Kashmir.
The project has the capability of generating an average annual energy of 102 MW.
The Project has been developed in shortest possible time and completed at a total cost of Rs. 52 billion.