Rawalpindi - A meeting to review the progress on Metro Bus Project was held yesterday at Rawalpindi Development Authority (RDA).  The meeting was chaired by Athar Bokhari, Chief Engineer RDA. Project Manager NESPAK and other relevant officers and contractors attended the meeting.

The chief engineer instructed the private construction companies to complete the remaining work, repairing and decoration with complete responsibility. He also instructed to work on roof leakage of Metro Bus Stations immediately. The meeting also discussed arrangement of proper lighting at Rialto Chowk Underpass. It was informed that Islamabad Electric Supply Company (IESCO) is continuously in contact and electricity connection will be provided soon. The chief engineer Metro Bus Project instructed to avoid any kind of negligence regarding lighting issue.

He said that additional work and repairs has been 95 percent completed. He ordered to complete all the work (100 percent) immediately.

He also instructed that work on elevators and escalators should not be stopped.