ISLAMABAD - The Engineering Procurement and Construction (EPC) Contract for first unit having capacity of 660MW (out of two units of 660MW each) and 5 years O&M Contract of 1320MW Jamshoro Coal Fired Power Project was Thursday signed between Jamshoro Power Company Limited (Genco-I) and the Siemens-HEI (Harbin Electric International) joint venture.
The contract was signed in the presence of the secretary, Ministry of Energy (Power Division), Chief Executive Officer of Genco Holding Company, the Commercial Counsellor of the Embassy of People's Republic of China and other officials from Ministry, GHCL / Gencos, Asian Development Bank, Siemens, Harbin Electric International, Project Consultants Mott Mcdonald, etc.
The signed Lot is being funded by the Asian Development Bank, and each unit will be completed within 42 months. EPC Contract price for Lot-I (unit 1 of 660MW and balance of plant) signed Thursday is $562 million.
This will be the first supercritical coal fired power project in public sector to be installed at Jamshoro, Sindh. EPC contract price of Lot-II (unit 2 of 660MW and expansion of balance of plant) is $313million which will be signed in next phase once financing arrangement is finalized.
Genco Holding Company CEO M Imran Mian in his speech, highlighted salient features of the project and stated that along with the EPC contract, a contract for five years' O&M of the project was also signed. This project will use 80percent imported sub-bituminous coal and 20 percent local Thar iignite and, as a result, cheaper energy will be generated to meet the future electricity need of the country.
Imran informed that arrangement for financing for second unit of similar capacity is underway at advanced stage and EPC will also be signed very soon in the try to bring both units as quickly as possible.
Imran acknowledged the support extended by the Power Division, Ministry of Energy, Asian Development Bank and other stakeholders to achieve this historic milestone.
Imran further expressed the hope that all stakeholders will work as the team to complete the project within 42 months.
Ministry of Energy (Power Division) Secretary Yousuf Naseem Khokhar also appreciated the efforts of the teams from ADB, GHCL and JPCL to achieve the milestone of contract signing of this project.